Cabreira Wind Farm, located in Cabreira Mountain, consists of 33 wind turbines with 600 kW unit power, corresponding to a total installed power of 19,8 MW.
The connection of the park to the power grid is made through a 60 kV power line with a length of 25 km that connects to Armamar Substation.
The environmental studies included:
Archaeological Monitoring was carried out during the construction phase.
Studies developed in 1998, from 2003 to 2005 and in 2011.
Environmental Assessment Studies
Preliminary Environmental Analysis of Areas for Wind Farm Expansion
Archaeological Monitoring during Construction phase
1998 - 2011
ENERGELEC, Empreendimentos Eléctricos
TPF Consultores