The building has a total gross area of 11,350 m2, spread over 3 underground floors for parking, ground floor with services and 12 floors with a total of 40 housing units of type T2 to T4. The external facilities include 591.4 m2 of total area.
For its implementation, the following studies were carried out:
- Geotechnical, topography, architecture, foundations and structures, including outdoor installations (comprising green areas, access roads, a nursery, a garden and a sports pavilion);
- Integrated fire safety study, with the characterization of active measures (electronic detection systems and means of combat) and passive measures (compartmentalization of fires and escape routes);
- Water distribution network (potable and fire fighting);
- Storm sewage network and wastewater drainage;
- Electrical and lighting installations and equipment;
- Mechanical installations and equipment (hydropressors, elevators and escalators);
- Telecommunications facilities;- HVAC facilities and equipment;
- Fire safety installations and equipment;
- Gas distribution network and acoustic study.