Tendais Wind Farm, located in Viseu, consists of 6 wind turbines with 2 MW of unit power and a total installed power of 12 MW.
The connection of the Wind Farm to the power grid is carried out through a 15 kV electric line with a 13 km extension that connects at the Castelo de Paiva substation.
The environmental studies included:
Environmental and Archaeological Monitoring was carried out during the construction phase and Environmental Monitoring during the initial exploration phase.
Environmental Assessment Studies (Wind Farm Expansion)
Environmental Impact Study
Environmental and Archaeological Monitoring during the construction phase
Environmental Monitoring, in the Initial Exploration Phase, of Avifauna, Flora, Vegetation and Chiropteran
2005 - 2011
ENERBIGORNE – Projectos de Energia
TPF Consultores