Doubling of the West Railway Line - Stretch Cacém – Meleças
Doubling of the West Railway Line - Stretch Cacém – Meleças
Doubling of the West Railway Line - Stretch Cacém – Meleças

The work comprised:

Dualling of the West Line between 18.270 and 20.300 km, involving earthworks, drainage, retaining walls, track (3 400 m and 8 switches) and catenary (94 poles and 8 gantries);
Viaduct variant to the Sintra Line, 169 m long and with 7 spans (2 of 17 m and 5 of 27 m). In addition to the civil engineering work inherent in the construction of the viaduct, track (1 680 m) and catenary (2 450 m) work was also carried out.

Assignment

Construction Works Supervision

Download PDF

Work's Value

4,1 Milhões

Date

1997 - 2000

Country

Client

REFER - Rede Ferroviária Nacional, E.P.

Companies

TPF Consultores

PENGEST

Sectors