The project integrated in the program of renovation of the Line of the Minho, understood the total reconstruction of the platform of roadand engenieering structures between Nine and Tandim, as well as the integral renovation of the track and assembly of catenary.
Besides the passengers' new station of Tandim, was also built a platform of goods with warehouse, platform of unloading, park of rail road material and, interface of load road worker.
The project included also an extensive remodelling / creation of road infrastructures, for access to the new platforms and interconnection of the inferior and superior passages with the road existent net.
The enterprise fulfilled functions of Co-ordination and Supervision of the works securing also the Coordinator's functions of the Security and Health in phase of Work
Construction Works Supervision
35
2002 - 2004
REFER - Rede Ferroviária Nacional, E.P.
TPF Consultores